Project Milestones

Milestone DescriptionEstimated Completion DateActual Completion DateAwarded to
RFP-Preliminary Engineering/Environmental Issued07/01/200407/14/2004N/A
Preliminary Engineering/Environmental Contract Awarded10/19/200410/19/2004TCF Architecture, Randy Cook-Principal
Land Appraisal10/01/200504/05/2006N/A
Land Purchase 10/31/200611/01/2006N/A
Preliminary Engineering/Environmental Contract Complete11/30/200602/01/2007N/A
Environmental-DCE/NEPA Update Complete07/15/201207/09/2012N/A
Project Management Contract Awarded12/31/201212/18/2012City of Port Townsend-Samantha Trone, PE
RFQ-Conceptual Design/Final Design Issued01/15/201301/07/2013N/A
Conceptual Design/Final Design Contract Awarded03/22/201303/22/2013TCF Architecture, Randy Cook-Principal
Project Managment Contract Complete-Phase 1*09/30/2013N/A
RFB-Construction10/16/2013N/A
Construction Management Contract Awarded*12/15/2013
Construction Contract Awarded12/17/2013
Conceptual Design/Final Design Contract Complete12/31/2013N/A
Construction Management Contract Complete12/30/2014N/A
Construction Complete12/30/2014N/A

 

* The Intergovernmental Project Management Contract with the City of Port Townsend has a clause in it that can extend the contract to include Construction Management through negotiations.

 