New Facility Progress Page
Project Milestones
Milestone Description | Estimated Completion Date | Actual Completion Date | Awarded to |
---|---|---|---|
RFP-Preliminary Engineering/Environmental Issued | 07/01/2004 | 07/14/2004 | N/A |
Preliminary Engineering/Environmental Contract Awarded | 10/19/2004 | 10/19/2004 | TCF Architecture, Randy Cook-Principal |
Land Appraisal | 10/01/2005 | 04/05/2006 | N/A |
Land Purchase | 10/31/2006 | 11/01/2006 | N/A |
Preliminary Engineering/Environmental Contract Complete | 11/30/2006 | 02/01/2007 | N/A |
Environmental-DCE/NEPA Update Complete | 07/15/2012 | 07/09/2012 | N/A |
Project Management Contract Awarded | 12/31/2012 | 12/18/2012 | City of Port Townsend-Samantha Trone, PE |
RFQ-Conceptual Design/Final Design Issued | 01/15/2013 | 01/07/2013 | N/A |
Conceptual Design/Final Design Contract Awarded | 03/22/2013 | 03/22/2013 | TCF Architecture, Randy Cook-Principal |
Project Managment Contract Complete-Phase 1* | 09/30/2013 | N/A | |
RFB-Construction | 10/16/2013 | N/A | |
Construction Management Contract Awarded* | 12/15/2013 | ||
Construction Contract Awarded | 12/17/2013 | ||
Conceptual Design/Final Design Contract Complete | 12/31/2013 | N/A | |
Construction Management Contract Complete | 12/30/2014 | N/A | |
Construction Complete | 12/30/2014 | N/A |
* The Intergovernmental Project Management Contract with the City of Port Townsend has a clause in it that can extend the contract to include Construction Management through negotiations.